High Speed 2 Railway Line

(asked on 22nd May 2019) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government what is the approximate quantity of steel rail required for the HS2 project.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 4th June 2019

As stated in the Working Draft Environmental Statement (p.136), the approximate total of steel required for the HS2 project is 1.94 million metric tonnes.

The procurements for contracts that will involve the purchase of steel have not yet concluded so no contract awards have been made. However, HS2 Ltd has already engaged with thousands of British businesses, to aid them in winning work on HS2. So far 98% of contracts for HS2, awarded directly and through the supply chain, have been won by British companies, with many more opportunities to come in the future. HS2 Ltd has let around £10bn worth of contracts and by the end of next year that will be around £20bn.

Reticulating Splines