Nuclear Reactors: Design

(asked on 12th March 2026) - View Source

Question to the Department for Energy Security & Net Zero:

To ask His Majesty's Government whether the generic design assessment process for advanced nuclear technologies is (1) faster, or (2) slower, and (a) more, or (b) less, costly, than for gigawatt-scale reactors.


Answered by
Lord Vallance of Balham Portrait
Lord Vallance of Balham
Minister of State (Department for Energy Security and Net Zero)
This question was answered on 26th March 2026

The scope and schedule of a Generic Design Assessment is set by the Requesting Party. By far the biggest influences on schedule, and hence cost, are the maturity and stability of the design, and the quality and timeliness of the Requesting Party’s submissions. Prior engagement with the UK regulators, and access to relevant information and judgements from overseas regulators are other notable factors in determining schedule and cost.