Question to the Department for Energy Security & Net Zero:
To ask His Majesty's Government whether the generic design assessment process for advanced nuclear technologies is (1) faster, or (2) slower, and (a) more, or (b) less, costly, than for gigawatt-scale reactors.
The scope and schedule of a Generic Design Assessment is set by the Requesting Party. By far the biggest influences on schedule, and hence cost, are the maturity and stability of the design, and the quality and timeliness of the Requesting Party’s submissions. Prior engagement with the UK regulators, and access to relevant information and judgements from overseas regulators are other notable factors in determining schedule and cost.