Electricity Generation

(asked on 20th March 2019) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask Her Majesty's Government what plans they have, if any, to permit Demand Side Response measures to be taken into account when assessing bids under the Capacity Market scheme, if and when the Scheme is re-started.


Answered by
Lord Henley Portrait
Lord Henley
This question was answered on 26th March 2019

Capacity Market auctions are technology neutral and all eligible technologies are able to compete on an equal basis. Demand side response (DSR) providers have been able to participate in all Capacity Market auctions, alongside other technologies, since the Capacity Market was established. We also held two “Transitional Arrangements” auctions for DSR in 2016 and 2017. The most recent T-4 auction, held in 2018, awarded agreements to 1.2 GW of DSR capacity. Capacity market agreements totalling over 4.7GW have been awarded to DSR through the CM so far, worth approximately £85million.