Ashington-Blyth Railway Line

(asked on 27th January 2021) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government, further to the allocation of £34 million to the scheme to restore passenger services to the Ashington–Blyth rail line, where the scheme lies within (1) the Rail Enhancement Schemes Pipeline and (2) the Governance for Railway Investment Projects (GRIP) process.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 9th February 2021

On 23rd January, the Government announced £34m for preparatory works to progress re-opening the Northumberland line to passengers. A Final Business Case is now being prepared by DfT, Northumberland County Council and Network Rail, with a view to seeking a ‘Decision to Deliver’ though the RNEP by the end of the year. The scheme is currently at stage 4 of the GRIP process.

Reticulating Splines