A21

(asked on 6th December 2018) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government what assessment they have made of the impact of improvements made to the A21 road since 2014; and whether such improvements have resulted in a reduction in traffic delays.


Answered by
Baroness Sugg Portrait
Baroness Sugg
This question was answered on 17th December 2018

Highways England regularly monitors the performance of the Strategic Road Network to ensure its efficient operation and performance.

The A21 Tonbridge to Pembury improvement scheme started construction in Spring 2015 and was completed in summer 2017.

The impact of the completed scheme, which is expected to reduce congestion and improve journey times, will be studied next year (2019) as part of Highways England’s programme of Post Opening Project Evaluation. This will consider journey times and other features of the performance on this section of the A21.