Abnormal Loads: West Midlands

(asked on 11th November 2025) - View Source

Question to the Department for Transport:

To ask His Majesty's Government, further to the Written Answer by Lord Hendy of Richmond Hill on 16 September 2024 (HL568), under which movement classification the movement notification to National Highways about the tram movement from the Very Light Rail Innovation Centre in Dudley to the Metro Maintenance Centre in Wednesbury on 15 February 2024 was made.


Answered by
Lord Hendy of Richmond Hill Portrait
Lord Hendy of Richmond Hill
Minister of State (Department for Transport)
This question was answered on 25th November 2025

The actual movement notification for the tram movements was submitted under ‘STGO AIL Cat 3’ on ref: RFS/3062 on the 25th January 2024.