Question to the Department for Energy Security & Net Zero:
To ask His Majesty's Government what assessment they have made of how many "zombie scheme" energy applications have secured grid connection offers in Scotland since 2021, broken down by local authority area.
The Department does not hold this data however, through reforms to the connections process, only projects that are ready and needed will be offered a connection, by requiring evidence of land access and permission to build, as well as how a project aligns with the Clean Power Action Plan.