Question to the Department for Business, Energy and Industrial Strategy:
To ask the Secretary of State for Business, Energy and Industrial Strategy, whether a Microgeneration Scheme Certificate is required to access a Smart Energy Generation payment.
Under the Smart Export Guarantee (SEG), generators using solar, wind and micro-combined heat and power (CHP) installations up to 50kW are required to demonstrate that their installation and installer are suitably certified to be eligible to receive SEG payments from a supplier. This may be a Microgeneration Certification Scheme (MCS) certificate, but the SEG also recognises that other schemes may be equivalent to MCS. Further details about the SEG eligibility requirements can be found at https://www.ofgem.gov.uk/publications/smart-export-guarantee-guidance-generators