Question
To ask the Secretary of State for Energy and Climate Change, what discussions she has had with her colleagues in the Department for Communities and Local Government and the Department for Environment, Food and Rural Affairs prior to the decision being taken to overrule the rejection of a planning application for gas storage made by Halite Energy in Preesall, Lancashire.
None. The Preesall Underground Gas Storage Facility development consent order application was redetermined by way of a written representation procedure pursuant to Rule 20(2) of the Infrastructure Planning (Examination Procedure) Rules 2010. All representations received under the 2010 Rules or otherwise were taken into account in the decision to grant development consent.