Renewable Energy: Construction

(asked on 14th March 2017) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, what assessment his Department has made of the completion dates for renewable energy projects across the UK for which (a) planning permission has been approved and (b) the installed capacity is to be equal to or above one gigawatt; and if he will make a statement.


Answered by
Jesse Norman Portrait
Jesse Norman
This question was answered on 21st March 2017

In England and Wales, the following offshore wind projects have development consent and capacities equal or higher than one gigawatt: Dogger Bank Creyke Beck A (1.2GW), Dogger Bank Creyke Beck B (1.2GW), Dogger Bank Teeside A (1.2GW), Dogger Bank Teeside B (1.2GW), Hornsea One (1.2GW), Hornsea Two (1.8GW) and Triton Knoll (1.2GW).

Hornsea One is currently under construction with target commissioning dates of 31 March 2019, 31 March 2020 and 31 March 2021 for its three phases. Completion dates for the other projects listed above are not known.

In Scotland, the Moray Firth offshore wind project has consent for 1.116GW. The completion date for this project is not known.