High Speed 2 Railway Line: Compensation

(asked on 11th January 2017) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what progress has been made by HS2 Ltd on introducing an alternative dispute resolution for landowners relating to compensation.


Answered by
Andrew Jones Portrait
Andrew Jones
This question was answered on 16th January 2017

An Alternative Dispute Resolution mechanism for the HS2 project will be in place by May, when land for the railway starts to be permanently compulsorily acquired.