Question to the Department for Business, Energy and Industrial Strategy:
To ask the Secretary of State for Business, Energy and Industrial Strategy, what progress has been made on the status of the proposed Trafford combined cycle gas turbine plant.
Following representations from the developer, as provided for under the Capacity Market legislation, an extension of 60 working days to 19 December has been granted for them to achieve the requirements of the Capacity Market progress milestone. The Secretary of State’s discretionary powers to extend a compliance period are designed to recognise situations where a little additional time can help a provider achieve a milestone, to the benefit of our security of supply.