Construction: Materials

(asked on 18th August 2021) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, with reference to the Construction Leadership Council's statement on Construction Product Availability on 22 June 2021, what steps his Department is taking to (a) support allocation transparency within the building materials supply chain and (b) protect smaller building firms from unfair practices in materials supply.


Answered by
Anne-Marie Trevelyan Portrait
Anne-Marie Trevelyan
Minister of State (Foreign, Commonwealth and Development Office)
This question was answered on 6th September 2021

At present, demand for building materials is outstripping supply due to high levels of global construction activity. Manufacturers are working hard to maximise production, but they are struggling to keep pace with demand due to lack of stock and Coronavirus-related disruption to production facilities, shipping and logistics.

The Government recognises the impact that this situation is having on many smaller building firms and we are working closely with the Construction Leadership Council’s (CLC) Product Availability Group to monitor and manage it.