Data Centres: National Grid

(asked on 4th November 2026) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what steps she is taking to ensure that prioritising data centres for electricity grid connections does not delay connections for (a) new housing and (b) essential public services in Bicester and Woodstock constituency.


Answered by
Michael Shanks Portrait
Michael Shanks
Minister of State (Department for Energy Security and Net Zero)
This question was answered on 12th November 2026

New prioritisation measures will enable strategically important demand projects of all types, such as housing and essential services, to access capacity released from the queue or reserved by Government.

Measures to prioritise strategic demand, including data centres, have been designed to avoid delaying other customers and will remain subject to network deliverability requirements.

Government has also confirmed its intention to proceed with aligning data centre connections after 2030 to regional limits to ensure data centre growth considers availability of resources including capacity needed for other types of demand.