Data Centres: National Grid

(asked on 4th November 2026) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, with reference to HM Treasury's document entitled Data Centre Covenant, published on 28 October 2026, whether she will require the publication of an assessment of the potential impact on (a) household and business electricity bills and (b) connection times for housing developments and essential public services before granting a data centre priority access to the electricity grid.


Answered by
Michael Shanks Portrait
Michael Shanks
Minister of State (Department for Energy Security and Net Zero)
This question was answered on 12th November 2026

Government is working closely with Ofgem and NESO on a package of demand connections reforms to tackle speculative applications and ensure the demand connections process is fair and efficient and supports timely connections in general. For the most strategically important data centres, we will consider facilitating ‘like-for-like’ transfers of existing data centre connection agreements, where needed to provide access to power pre-2030. This approach is designed to maximise benefit to Great Britain while minimising impacts on wider customers.

Data centres seeking enhanced support must meet the tests set out in the Covenant, including covering any energy costs they create so these do not fall on households or businesses.

Decisions on priority access will consider efficient use of grid capacity and impacts on other customers. Further details of the assessment process and prioritisation framework will be set out in due course.