To ask the Secretary of State for Energy and Climate Change, with reference to the Written Statement of 18 June 2015, HC WS40, whether her Department plans to offer support under the Renewables Obligation to the proposed Nocton Fen wind farm.


Answered by
Andrea Leadsom Portrait
Andrea Leadsom
This question was answered on 29th June 2015

We have proposed that onshore wind projects wishing to access the grace period allowing them entry to the Renewables Obligation beyond our propose closure date of 1 April 2016 will, by 18 June 2015, have to have planning consent, a grid connection offer and acceptance, and evidence of land rights for the site on which their project will be built. The precise grace period eligibility requirements will be determined through the legislative process and are subject to approval by Parliament. It will be for the developer of each individual project to determine whether they meet those eligibility requirements.