Hinkley Point C Power Station

(asked on 16th March 2016) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Energy and Climate Change, pursuant to the Prime Minister's oral Answer of 16 March 2016, Official Report, what part of the text of the agreement on Hinkley Point C nuclear power plant provides that there will be no payment by the Government unless the power station goes ahead and is built efficiently by EDF.


Answered by
Andrea Leadsom Portrait
Andrea Leadsom
This question was answered on 23rd March 2016

My rt. hon. Friend the Secretary of State will make a final decision regarding Hinkley Point C once EDF have reached a Final Investment Decision. The terms of the contract will be published (with only the most commercially sensitive information removed) once it has been entered in to by the parties.

In October 2015, the Government laid a minute before Parliament setting out at a high level the terms of the agreement reached with EDF in respect of the Hinkley Point C power plant:

http://qna.files.parliament.uk/qna-attachments/425357%5Coriginal%5C20151021%20Minute%20to%20Parliament%20HPC%20contingent%20liabilities.docx.