Electricity Generation

(asked on 4th July 2017) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, whether the T-4 capacity market auction for delivery in October 2021 will take place in February 2018; and and if he will make a statement.


This question was answered on 12th July 2017

On 15th June National Grid released the capacity market timetable for 2017/18 and within it they have indicated that the T-4 auction will start on 6th February. Please find a link to the timetable document here: https://www.emrdeliverybody.com/Lists/Latest%20News/Attachments/109/Capacity%20Market%20Operational%20Plan%202017.pdf