High Speed 2 Railway Line

(asked on 21st October 2019) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, if he will list all payments to WS Atkins for work (a) on and (b) about High Speed Two made by (i) his Department and (ii) HS2 Ltd.


Answered by
Paul Maynard Portrait
Paul Maynard
Parliamentary Under-Secretary (Department for Work and Pensions)
This question was answered on 24th October 2019

The costs paid to WS Atkins on the HS2 project date back to 2009. The department has paid £827,218.15. This principally relates to the passage of the hybrid Bill. HS2 Ltd has paid £85,672,231.94. This principally relates to engineering work on Phase One of the project.

Reticulating Splines