Harperbury Free School

(asked on 8th February 2016) - View Source

Question to the Department for Education:

To ask the Secretary of State for Education, by what process her Department ensured the site secured for the proposed Harperbury Free School (a) was large enough and (b) met other requirements to be suitable for a secondary school with the capacity for up to 840 students and 70 staff.


Answered by
Edward Timpson Portrait
Edward Timpson
This question was answered on 23rd February 2016

Approval to build the school on the site is subject to the views of the Local Planning Authority. They first raised concerns, alongside a range of other concerns arising from its location in the Green Belt, to my officials in March 2015.

Discussions between officials at both Departments did identify that two adjacent properties could be purchased to provide additional car parking. However, the nature of the sale of the remainder of the former hospital site to a residential developer meant that further land could not be released for the school. Even if additional land were made available, there remain substantial risks associated with developing this Green Belt site.

Reticulating Splines