Question to the Department for Business, Energy and Industrial Strategy:
To ask the Secretary of State for Business, Energy and Industrial Strategy, what steps his Department is taking to implement resilience recommendations 3 and 4 within the Storm Arwen electricity distribution disruption review, published on 9 June 2022.
The Energy Emergencies Executive Committee (E3C), of which the Department for Business, Energy and Industrial Strategy (BEIS) is a member, is responsible for implementing actions set out in the Storm Arwen Review Final Report. This follows successful practice following previous reviews with cooperation with industry partners, as appropriate.
Oversight by officials of BEIS will be achieved through a newly established Storm Arwen Implementation Steering Group to ensure timely and effective delivery of these actions.