Question to the Department for Levelling Up, Housing & Communities:
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 11 April 2019 to Question 242144 on Buildings: Insulation, if he will publish the revised start date for the testing of non-aluminium composite materials as a result of the damage to the test rig.
We are advised that testing of non-aluminium composite materials, should start in the week of 29 April 2019, following completion of calibration tests.