Sizewell C Power Station

(asked on 24th April 2024) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, with reference to the press release dated 15 April 2024 issued by the company Framatome, entitled Framatome has signed contracts worth multi-billion euros for Sizewell C in the UK, what the monetary value is of the contracts referred to; and for what reason the contracts were signed in advance of a final investment decision for the construction of a new nuclear power station at Sizewell.


Answered by
Andrew Bowie Portrait
Andrew Bowie
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 1st May 2024

Agreeing contracts with major suppliers like Framatome means that the Sizewell C project can agree pricing and confirm manufacturing slots within the supply chain. This will help maintain the project’s schedule and manage overall costs, supporting Sizewell C’s value for money.

The value of these contracts is commercially sensitive, and the timing of payments under these contracts will be subject to Notices to Proceed that will be issued by Sizewell C Limited.