Question to the Department for Business, Energy and Industrial Strategy:
To ask the Secretary of State for Business, Energy and Industrial, if he will provide an update on the delivery of the Grangemouth Renewable Energy Plant which was awarded a Contract for Difference in 2017 as part of CfD allocation round two.
The Low Carbon Contracts Company (LCCC) announced on 19 October 2018 its decision to terminate the contract for difference (CfD) awarded to Grangemouth Renewable Energy Plant for failing to make sufficient progress by the Milestone Delivery Date. The press release is available on the LCCC’s web site - https://www.lowcarboncontracts.uk/
CfDs are private law contracts between a generator and the LCCC, and decisions relating to whether a generator has met its milestone requirement are for the LCCC.