Great Western Railway Line: Electrification

(asked on 19th December 2019) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what plans he has to electrify all or part of the Great Western mainline between Penzance, Plymouth and Paddington in the next Network Rail control period.


Answered by
Chris Heaton-Harris Portrait
Chris Heaton-Harris
Secretary of State for Northern Ireland
This question was answered on 7th January 2020

There are no immediate plans to electrify all or part of the Great Western mainline between Penzance, Plymouth and Paddington in the next Network Rail control period. However, Network Rail is currently preparing a Traction Decarbonisation Network Strategy (TDNS), which is due to report in 2020. This will indicate where routes might be electrified or where hydrogen or battery trains could be deployed. The TDNS will therefore inform future decisions about electrification.