To ask the Secretary of State for Energy and Climate Change, what assessment he has made of the future operating life of Dungeness B nuclear power station; and if he will make a statement.
On 20 January 2015, EdF announced that the life of Dungeness B has been extended to 2028. This was a decision for EdF as the owner and operator to make in consultation with the regulator.
There is no regulatory requirement for nuclear plant operators to gain permission from the Office for Nuclear Regulation (ONR), for a plant life extension. Plant operators must instead demonstrate that plant will continue to run safely and in compliance with site licence conditions in the course of regular ONR assessments. However, in the case of Dungeness B, EdF and the ONR agreed it would be beneficial for ONR to review the life extension proposals in advance of the life extension announcement, which they have done.
Separately, in order to ensure that the extension does not impact on the UK taxpayer, the Nuclear Decommissioning Authority (NDA) reviewed the impact of the decision on the UK’s Nuclear Liability Fund last year. The NDA approved the life extension to the plant. The assessment showed net savings rather than net costs.