To ask the Secretary of State for Culture, Media and Sport, whether the (a) County Durham, (b) Oxfordshire, (c) Hampshire, (d) Essex and (e) Wokingham phase 2 broadband projects received bids or offers from suppliers other than BT.
County Durham, Hampshire and Essex are procuring their phase 2 broadband projects using the broadband framework. BT is the only supplier on the framework.
Oxfordshire has undertaken its phase 2 procurement through a change control process using its existing contract which was procured through a process advertised in the Official Journal of the European Communities (OJEU) independently from the broadband framework.
West Oxfordshire is completing its own OJEU procurement with alternative supplier partner Cotswold Broadband.