Question
To ask the Secretary of State for Energy and Climate Change, which port, harbour and coastal locations in the UK have a National Grid connection enabling a power plant connection of over 300MW.
Connections to the high voltage electricity transmission are a matter for National Grid, in its role as System Operator.
National Grid publishes information on current and future transmission capability, generation connections and development timescales in its annual Electricity Ten Year Statement and Customer Connection Interface Tool. These documents are available at: