Mobile Phones: Northern Ireland

(asked on 7th July 2014) - View Source

Question to the Department for Digital, Culture, Media & Sport:

To ask the Secretary of State for Culture, Media and Sport, what estimate he has made of how many households in Northern Ireland will benefit from each phase of the Mobile Infrastructure Project; and what the current expected date of completion is for each phase of that project in Northern Ireland.


Answered by
Lord Vaizey of Didcot Portrait
Lord Vaizey of Didcot
This question was answered on 14th July 2014

DCMS officials and our delivery partner Arqiva are continually reviewing potential locations for masts with the intention of providing coverage to as many premises as possible. Various challenges will have an impact on the number of premises we can reach and completion dates for individual masts, such as finding a suitable and sensitive location for a mast, obtaining planning permission, and ensuring masts can connect back into the existing network.