Offshore Wind Manufacturing Investment Support Scheme

(asked on 22nd June 2023) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, how much offshore investment has been allocated to firms in (a) Teesside Combined Mayoral Authority area, (b) North of Tyne Combined Mayoral Authority area and (c) Wales.


Answered by
Graham Stuart Portrait
Graham Stuart
This question was answered on 27th June 2023

In the Teesside Combined Mayoral Authority, grants from the Offshore Wind Manufacturing Investment Scheme (OWMIS) fund totalling £37 million supported South Tees Development Corporation’s Teesworks Offshore Manufacturing Centre and SeAH Wind’s monopile foundation facility. In the North of Tyne Combined Mayoral Authority, OMWIS fund grants totalling £21 million supported Smulders to enable the manufacture of transition pieces at their facility and JDR Cables to build a subsea cable factory. No OWMIS grants have been allocated to firms based in Wales.