Tidal Power: Finance

(asked on 17th February 2023) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, whether he expects the budget for ringfenced support for tidal stream energy in Allocation Round 5 for Contracts for Difference will be at least as large as that provided in Allocation Round 4.


Answered by
Graham Stuart Portrait
Graham Stuart
This question was answered on 22nd February 2023

Final parameters for Allocation Round 5 (AR5) are currently under development. This involves a careful analysis of all technologies available in AR5, including tidal stream energy, against the Government's legal obligations. The Government is considering the appropriate parameters to ensure a competitive auction and the sufficient deployment of all technologies. Budgets set will reflect parameter decisions. A Budget Notice for AR5 with the full auction and budgetary details will be published in March 2023.