Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, if she will have discussions with National Grid on ensuring that the statutory consultation on the Norwich to Tilbury infrastructure project does not take place until the Electricity System Operator offshore coordination study has concluded.


Answered by
Graham Stuart Portrait
Graham Stuart
This question was answered on 21st February 2024

As the statutory consultation process is not led by Government, there have not been discussions between the Secretary of State and National Grid Electricity Transmission (NGET) on the timing and alignment of its consultation on this project. NGET has however publicly stated that it will ensure that the results of the Electricity System Operator East Anglia study will be considered fully.