Question to the Department for Business, Energy and Industrial Strategy:
To ask the Secretary of State for Business, Energy and Industrial Strategy, what estimate he has made of the levelised cost of offshore wind farms commissioning in 2022.
The Department’s Electricity Generation Cost Report[1] published on gov.uk sets out levelised cost of electricity estimates for a range of technologies, including offshore wind.
[1] https://www.gov.uk/government/publications/beis-electricity-generation-costs-2020