Question
To ask the Secretary of State for Energy and Climate Change, for what reasons the construction cost of the planned Hinkley Point C power station has reduced from £24.5 billion to £18 billion.
The £24.5 billion figure included financing costs (interest and guarantee costs) assuminga £16 billion IUK guarantee. The £18 billion figure is not directly comparable as it does not include these financing costs.