(12 years, 10 months ago)
Commons Chamber15. What progress has been made on the northern hub railway project.
The Government have given the go-ahead for the construction of the Ordsall chord and the electrification of the north trans-Pennine route between Manchester and York via Leeds. These schemes will allow faster trains between the north-east, Leeds, Manchester and Liverpool. Network Rail is undertaking further work on the remaining northern hub schemes. We will consider these in developing the Government’s high-level output specification for rail investment from 2014 to 2019.
Does my right hon. Friend agree that if we could complete all parts of the scheme it would be a tremendous demonstration of our continued commitment to further investment in the existing rail structure and to further investment in the north-west?
This is exactly the sort of issue that we will consider in preparing our HLOS statement. I recognise the crucial importance for the northern economy of improving rail connections in the north. That is why we have already given the go-ahead to such important parts of the northern hub—earlier than many expected—and we will of course look very carefully at the whole project. It certainly looks to have a good business case, but delivering it will depend on what is affordable.
(13 years, 10 months ago)
Commons Chamber6. What plans he has for the reform of rail franchising; and if he will make a statement.
11. What plans he has for reform of rail franchising; and if he will make a statement.
I thank my hon. Friend for his question. I have been impressed with the work done by him, the Harrogate chamber of commerce and Harrogate business interests to make the case for improved rail services between Harrogate and London. I would encourage them to continue that input when the consultation takes place on re-letting the east coast franchise. We will, of course, take those representations into account in our decisions on Harrogate services.
Given the announcement last week that the west coast main line franchise will be up for renewal, how soon does the Minister think we will see the extra carriages and, perhaps, the extra trains that we need to relieve the severe overcrowding on the line, particularly for my constituents in Lancaster?
The Government will be funding 106 extra carriages on the west coast main line, which are due to come into operation with the new franchise. Some of those carriages will be available in a new train that will be available earlier, once its testing period has been completed. At that point, it will be available for Virgin to sub-lease, if ordinary commercial terms can be agreed.
T8. I know that the Minister is aware that Fleetwood has a railway line that has been redundant since the 1960s but which has most of its infrastructure intact. What hope can she offer my constituents that there may be a chance of reopening the line and providing much-needed regeneration to the town?
I know that my hon. Friend has championed this cause, and I enjoyed my visit to the disused rail line. Programmes such as he outlines can confer significant local benefits, but it is primarily for the local authorities to identify the funding to restore railway lines and, importantly, to identify the funding for any ongoing subsidy that is needed. Local authorities may well wish to consider those options in order to enhance economic growth in their areas.