(11 years, 4 months ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
I have discussed this with the Secretary of State, and he says he is open to the idea, although a number of practical difficulties need to be overcome. Providing that they are, however, I hope, as I said just now, that the Government will adopt the property bond, because it will give comfort to my right hon. Friend’s constituents and mine.
May I give my hon. Friend the reassurance that my right hon. Friend the Secretary of State and I gave during the Second Reading of the paving Bill? As a result of the 10th judicial review—we won the other nine—we will reconsult on the compensation schemes. Let me say categorically that consideration of, and consultation on, a property bond will be one of the options.
As ever, my hon. Friend makes his point powerfully and well. I hope that the Minister has listened to what he said. He is right to say that the west midlands has suffered, and I think that it has suffered in a way that has not been replicated in other parts of the United Kingdom.
In May, I tabled a question asking my right hon. Friend the Secretary of State for his own assessment of the impact of the proposed HS2 route on ancient woodland. The response that I received in the Official Report on 6 June at column 1224W seemed, sadly, to indicate a belief in Government that such destruction is a price worth paying. It also noted that certain mitigation measures were being proposed, including the construction of a tunnel to avoid one ancient wood and movement of a line to minimise land take within another. That is simply not good enough. When we consider the vast sums of public money being committed we realise that the damage is inordinately large. As a minimum, mitigation should be proportionate and applied comprehensively for any ancient woodland lost or damaged as a result of the project. That should be based on the Lawton principles on habitat networks and landscape scale impact already enshrined in the Government’s widely welcomed natural environment White Paper of 2011. If, as it is claimed, HS2 is meant to be a world-class transport project, it should demonstrate world-class practice when it comes to the avoidance of damage and the showcasing of the very best practice in mitigation.
Further insult has been added to injury by the publication of a poorly written, half-finished environmental statement, which neglected to include crucial ecological surveys and assessments that are required for communities to respond effectively. The environmental statement sadly misunderstands the complexity and national significance of the habitats being damaged. For example, the summary states that
“at present there are no route-wide significant effects on habitats”.
Extraordinary. That is clearly not the case, given the national significance of ancient woodland, which is recognised in the national planning policy framework. I tabled another question in May—it appears at column 1224W in the Official Report of 6 June—about what discussions were taking place with the Department for Environment, Food and Rural Affairs on minimising the impact of construction on ancient woodland. The evidence of the environmental statement is that there has been far too little such discussion, and the result is a statement that pays mere lip service to environmental protection.
It does not need to be this way. Done properly, HS2 would provide the Government with a golden opportunity to showcase the very best of British construction. However, if it is to be the world-class and truly green transport solution that it purports to be, far greater respect for the natural environment needs to be demonstrated, or the opportunity will sadly be lost.
In the light of the impacts that I have highlighted, I call on my right hon. Friend the Minister, and the Government, with whom I have had the honour of serving, to look again at the proposed route for HS2. In opposition, as I have said, my party championed a route that followed existing transport corridors, a tried and tested method used across Europe, which minimises environmental damage. I know that phase 2 of the route is an attempt to do that, but of course in southern Staffordshire it is not possible, because of the need to link to the existing and most environmentally damaging route: phase 1. That policy position is now, ironically, receiving favour from the current Opposition party, whose route the coalition Government have now adopted. It is incredible.
I call on my right hon. Friend, rather than cutting a destructive swathe through previously unblemished countryside, to think again and deliver a route that better respects the environment we all treasure. I hope that in his answer he will address the following six questions of which, Mrs Osborne, I have given him prior notice—so he has no excuse not to answer. He is waving his speech, so I hope he will answer these questions in detail: first, will he look further at how the loss of ancient woodland can be minimised? Secondly, what assessment has been made of how many hectares of ancient woodland will be lost? Thirdly, how much of the £33 billion—of course, that sum has now gone up—will be spent on seeking to avoid loss of woodland and on the creation of new woodland as part of the mitigation process? Of course, I pointed out earlier that ancient woodland cannot be replaced overnight. Ancient woodland is woodland formed in 1600 and before.
No, it is not; ancient woodland is described as existing from 1600.
I will not give way to my right hon. Friend, simply because I think others want to take part in the debate. He can answer that point, if he wishes, in his speech.
My fourth question is whether my right hon. Friend will undertake to involve DEFRA and environmental organisations more fully. Fifthly, what say and involvement will communities have in any mitigation planting? Finally, will he ensure that the full environmental impact assessment, when it is published alongside the Bill, will be a major improvement on the somewhat inadequate work that was released earlier in the spring? I thank you for your indulgence, Mrs Osborne, and look forward to hearing from others in the debate.
On the Minister’s visit—by the way, he did not write to me to say that he was visiting—
Far be it from me to criticise my right hon. Friend. On his private visits, has he been to one of the newer woodlands to see for himself the difference between newly planted woodland and a wood of the type my right hon. Friend the Member for Chesham and Amersham (Mrs Gillan) describes that has existed for 300 or 400 years?
I take on board my right hon. Friend’s point about the number of trees, but I am not 100% convinced that 4 million new trees along the line of route is not the right number. Of course, that is only part of the remedial action that the Government and HS2 Ltd will take to protect the environment, which I shall address in greater detail later.
My right hon. Friend also raises an important point about community forums and the interactive dialogue between communities and HS2 Ltd. I will be frank with her: we get a variety of reports of those meetings. Some reports have been extremely positive, saying that people have found the meetings extremely helpful. As she will know from her correspondence with me on behalf of her constituents, they have been concerned about some of the meetings that have taken place in her constituency, and I accept that point. I have noted the criticisms that she has drawn to my attention. We have certainly spoken to HS2 Ltd and we or it will address the concerns of several of her constituents, because we believe that it is important that there is a proper dialogue between communities and HS2 Ltd, and that people work together. Even if people do not necessarily agree with the project, that is the important thing. Because I and the rest of the Government believe that the project is in the national interest and should go ahead, we must work with local communities, and local and national organisations, to ensure that we get the best project that causes the least damage to the environment.
In addition to the new trees that will be planted, we are examining opportunities to enhance existing habitats or create new woodland areas and wildlife habitats, but we must be mindful that it is not possible—unfortunately, and as much as I would love to have it in my gift—to avoid completely all sensitive areas. We have already made every effort to avoid sites that are of importance for their international ecological value and areas of national designation, such as the Chilterns area of outstanding natural beauty. In this instance, of the 13 miles of route through the area, less than 2 miles will be at or above the surface. Compared with the phase 1 route that was originally subject to consultation in 2011, there will be a more than 50% increase overall in tunnel or green tunnel, and the initial preferred scheme for phase 2 has no impact on national parks or areas of outstanding natural beauty.
When it comes to minimising impact on ancient woodlands, the Department and HS2 Ltd take their obligation to conserve them extremely seriously. Through careful design of the route and strict controls during construction, we are seeking to reduce, as far as practicable, any impacts. For example, the provision of a tunnel at Long Itchington avoids the ancient wood there, and a retained cutting minimises land take at South Cubbington wood.
Ancient woodlands, as everyone who has taken part in or has listened to the debate accepts, are a very important part of our natural heritage. However, as I have said, it is, sadly, not possible to build a railway without any effects on important environmental sites. Other factors, such as the location of people’s homes, have to be taken into account as well. The Government have to strike a balance between a range of important considerations. That debate has taken place to good effect in the constituency of my hon. Friend the Member for Lichfield, where the original route has been moved away from those places where the majority of people live. Designs have also been developed to avoid important employment areas and to ensure that local conditions for growth are not missed.
I hope from the way my hon. Friend is nodding in the affirmative that he is appreciative and accepts that that was the right thing to do.
To provide an effective outcome for the natural environment, I strongly believe that we have listened and engaged, and we will continue to engage with those non-governmental organisations with an interest in the natural environment. The Woodland Trust, the Wildlife Trusts, the RSPB and other groups already form part of the debate through my regular environmental round-table meetings. They are already proving effective, and as a result we are implementing plans for a design panel to inform the aesthetics of the detailed design.
I assure my hon. Friend that we will be providing suitable compensation for any ancient woodland that is lost, following the best practice recommended by our ecologists, which is developed in conjunction with Natural England. We will also be examining opportunities to enhance existing woodland and to create new woodland areas and wildlife habitats. With more than 22,000 ancient woodlands in England and Wales, it is impossible to avoid them all. That being the case, we believe that it is appropriate to provide some form of compensation when avoidance is not possible.
Current best practice, which builds on methods employed for other major infrastructure projects, such as High Speed 1 and the M2 widening scheme, includes the relocation of the ancient woodland soil with its seeds to allow it to regenerate over time, together with the planting of native trees of local provenance. Ten years’ monitoring undertaken by environmental specialists has shown that new areas of habitat were successfully created along the HS1 route, including for protected species such as the dormouse.
It should be noted also that HS2 has committed to seeking no net loss of habitats. When ancient woodlands are affected, it will result in a larger area of woodland being created than the area lost.
(12 years, 1 month ago)
Commons ChamberI hope that the hon. Gentleman will agree that the answer that I have just given is a significant boost not only to the Welsh valleys, but to the main line from Cardiff to Swansea. It will create tremendous opportunities for regeneration for business and other passenger travel, and there will be the ancillary advantage of changes and improvements to the rolling stock once the project has been completed.
Having just received a speeding fine from South Wales police for going at 35 mph in a 30 mph zone—it was quite a shock for me this morning—the news about electrification and all the other good news that the Minister mentions greatly encourages me to use the railways in future.