Nuclear Management Partners (Sellafield) Debate

Full Debate: Read Full Debate

Nuclear Management Partners (Sellafield)

Mike Weir Excerpts
Tuesday 13th January 2015

(9 years, 11 months ago)

Commons Chamber
Read Full debate Read Hansard Text

Urgent Questions are proposed each morning by backbench MPs, and up to two may be selected each day by the Speaker. Chosen Urgent Questions are announced 30 minutes before Parliament sits each day.

Each Urgent Question requires a Government Minister to give a response on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Ed Davey Portrait Mr Davey
- Hansard - - - Excerpts

The NDA has approached some of its key decisions incredibly professionally, including the renewal of the contract and the review of the model that led to the recommendation to me for the change under discussion. I pay tribute to the NDA for the work it has done. It will, of course, be taking on a bigger role in the new model, so it will need to skill up, hire more expertise and fill the vacancies referred to by my hon. Friend. That was part of the questioning that I and others undertook to ensure that the transition process and the resulting process are successful.

Mike Weir Portrait Mr Mike Weir (Angus) (SNP)
- Hansard - -

Obviously, we need to deal with the cost of legacy waste, but as well as announcing the change in the contract the NDA has announced an increase in the estimated cost of cleaning up the site, which now comes to a staggering £110 billion over 120 years. Given those figures and that time scale, how can the Secretary of State possibly give the assurance he gave to the hon. Member for Newport West (Paul Flynn) that the costs of new nuclear will be met by the companies, which may well not be around in anything like 120 years?

Ed Davey Portrait Mr Davey
- Hansard - - - Excerpts

Let us be clear that those costs relate to decommissioning the legacy waste. In answer to the hon. Member for Newport West, I was referring to the negotiations with EDF and its partners on the strike price for the new build at Hinkley Point C. That will include the cost of decommissioning, so that is in the price. Legislation went through this House under the previous Government to set up the nuclear liabilities fund and to ensure that it is independent and ring-fenced so that the moneys that go into it are properly managed. We have done a huge amount of work to ensure that that ring-fenced resource will grow and meet the future decommissioning costs.