Asked by: Michael Payne (Labour - Gedling)
Question to the Department for Environment, Food and Rural Affairs:
To ask the Secretary of State for Environment, Food and Rural Affairs, what steps his Department is taking to support the improvement of flood (a) defences and (b) resilience in Gedling constituency.
Answered by Emma Hardy - Parliamentary Under-Secretary (Department for Environment, Food and Rural Affairs)
Environment Agency inspection of flood risk management assets defending the southern edge of Gedling did not identify any significant damage following winter storms. Maintenance of these assets can include blockage removal, vegetation management, and further interventions where needed, such as recent embankment repairs in Gedling. The Environment Agency estimate that c.£121,000 was spent on maintenance in Gedling in 2023/24, with approximately £300,000 planned for 2024/25.
There are no capital schemes planned in the constituency for this 6-year programme as the River Trent is well defended, benefitting from the £45M 2012 Nottingham Trent Left Bank scheme.
The Environment Agency has several strategic programmes in the constituency which may be added to our future capital pipeline.