Thursday 25th June 2015

(8 years, 10 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Michael Dugher Portrait Michael Dugher (Barnsley East) (Lab)
- Hansard - -

I thank the Secretary of State for advance sight of his statement.

Let us be absolutely clear: the Government’s total failure to deliver a fit-for-purpose railway has today been completely and damningly exposed. First, the publication of the latest national rail passenger survey—I note the Secretary of State did not mention it—shows that passenger satisfaction has dropped once again. Now we have the Secretary of State announcing that vital investment projects, such as electrification of the midland main line, which he promised to deliver, are being shelved owing to his repeated failure to get a grip of Network Rail. The electrification of the trans-Pennine express railway line between Manchester, Leeds and York has also been shelved—so much for the northern powerhouse—and we remain concerned about the future of the electrification of the Great Western line.

The Secretary of State spent the election campaign repeating promises that he knew he would break after the election. That is what has been revealed today. The truth is that passengers have had to endure a catalogue of failure on our railways by Ministers since 2010. There was the Christmas rail chaos, which the Secretary of State referred to, although he neglected to mention that Ministers had been warned about that and failed to act. While delusional Ministers talk about “fair fares” and “comfortable commuting”—which is a world away from the misery for commuters at London Bridge—there have been inflation-busting fare rises of on average more than 20%. We have also seen the collapse of the west coast franchise competition, which cost the taxpayer £50 million. Ministers may try today to shift all the blame to Network Rail, but this happened on the Government’s watch and the responsibility for the mess lays squarely with the Government.

Let me turn to a number of specific questions. Will the Secretary of State confirm that when the Government placed the development of key Network Rail projects on hold for up to two years after the 2010 election, important preparation work was not undertaken, and therefore, as the rail regulator has said, they committed to the projects in 2012 based on “limited development work”? We know that Network Rail started to put together a list of projects that would be axed back in November. Why has it taken so long for the Government to reveal them to the House and to be honest with the travelling public? Crucially, can the Secretary of State confirm that he received a report on 1 September last year on the state of those programmes from Network Rail, his Department and the regulator? He has refused to publish it. Why did he sit on the report and pretend to the public that everything was fine until after the election?

Labour first raised the issue of delays to the Great Western project in the House more than a year ago. Why has it taken so long for the Government to admit that there were fundamental problems with the project? Why did the Secretary of State not listen to the Transport Select Committee six months ago when it warned that key rail enhancement projects had

“been announced by Ministers without Network Rail having a clear estimate of what the projects will cost, leading to uncertainty about whether the projects will be delivered on time, or at all”?

Why did he not raise the alarm when the estimated cost of electrifying the midland main line rose from £250 million to £540 million and then to £1.3 billion; or when the cost estimates for Great Western electrification rose from £548 million to £930 million and then to £1.7 billion?

Just two weeks ago, the Secretary of State refused to answer my questions about the need to tackle the failures at Network Rail and whether he was planning changes to Network Rail. Will he explain why he has dithered for so long when he has had the power to exert more ministerial responsibility over Network Rail, including by appointing a special director, since September last year?

The Opposition have warned time and again that fundamental change in how our railways are run is needed, that Ministers need to get a grip, that passengers should have a proper voice and that more public control is needed. We welcome the appointment of Sir Peter Hendy as chairman of Network Rail, and we will look carefully at some of the other announcements that the Government have made.

The news today exposes a catalogue of failure by Ministers, and it deals a fatal blow to the Government’s claim that they are delivering a better railway for passengers. Is it not clear that the Government’s real legacy is one of rail fare hikes, plummeting passenger satisfaction, ongoing disruptions and delays, major projects running years behind schedule, promises of vital investment betrayed, and a railway that is not fit for purpose, and all the while out-of-touch Ministers sat in Whitehall overseeing a complete and utter shambles?

Lord McLoughlin Portrait Mr McLoughlin
- Hansard - - - Excerpts

It is true that I have been Transport Secretary for two and a half years. Despite the catalogue of terror that the hon. Gentleman has outlined, over those two and a half years there have been only two occasions on which the Opposition have chosen to debate transport on Opposition days. One was a day after I was appointed, and the other was on the day that the hon. Gentleman’s predecessor was sacked as shadow Transport Secretary. With regard to their warning us and wanting the subject lifted up the political agenda, we have heard nothing from the Opposition, because they are truly embarrassed by their record, whereas we have invested in the railways, lifted them and given encouragement to the railway industry.

Today I have made no cuts whatever to the rail investment strategy—the largest rail investment strategy that has ever taken place. The amount of money invested is exactly the same as it was last week—the budget within which the strategy has to be delivered. I will take no lessons from a Labour party that in 13 years electrified 10 miles of railway lines; we have electrified more this year than it did in all that time. Then there is the £895 million project to rebuild the railways around Reading and to remove major bottlenecks; the £750 million transformation and upgrade of Birmingham New Street station; the refurbishment of Nottingham station, with all the investment going into it. There has been more investment in Nottingham in the last five years than was seen in the 13 years of the last Labour Government. Then there is the new station built at Wakefield; the completed Ipswich Chord and the Doncaster Chord; phase 1 of the £6.5 billion Thameslink project; the completion of Crossrail tunnelling. I could go on a lot more, Mr Speaker. I will take no lectures. I am determined to get on top of, and see the delivery of, those programmes, which are so important for our constituents.