Louise Ellman
Main Page: Louise Ellman (Independent - Liverpool, Riverside)Department Debates - View all Louise Ellman's debates with the Department for Transport
(13 years, 11 months ago)
Commons ChamberI thank my hon. Friend for that question. He is quite right to observe that we must get the balance right between building large new infrastructure projects and maintaining existing services. I have been out this morning to the site of the Blackfriars station development and seen just how incredibly difficult it is to build such a major project on a running railway line with trains passing backwards and forwards. It is very complex, and allowing a little extra time will ensure that we do not have catastrophic disruption during the programme.
I welcome the news of investment in rail, although I am concerned about the three-year delay in the electrification of the Liverpool-Manchester-Blackpool line as well as the uncertainties on electrification of the great western line. Will the Secretary of State explain the percentage growth in rail that he is planning within these figures so that rail can grow without overcrowding and without the overpricing that drives people off the railways?
I do not know where the hon. Lady gets the idea about three years’ delay with north-west electrification. As I said, the Manchester to Newton-le-Willows section will be completed in 2013. Work will start next year. The team that is doing the work will then roll on to complete the electrification of the Liverpool-Manchester section and finally the Preston-Blackpool section. It will all be completed by 2016.
Let me explain the time scale. Electrification will allow the electric carriages released by the delivery of the new Thameslink carriages to be deployed. There is no point completing that electrification, except for the section from Manchester to Newton-le-Willows, until those electric carriages are available. The timetabling is perfectly logical and the early completion of Manchester to Newton-le-Willows will allow brand-new electric trains to be operated on the Manchester to Scotland routes.
The hon. Lady asked about capacity. The total announcements on Crossrail, Thameslink and the additional 650 carriages to be delivered before 2015 will amount to a 17% increase in the capacity of the network.