Energy Bill [HL] Debate

Full Debate: Read Full Debate
Department: Wales Office
Tuesday 12th April 2016

(8 years, 1 month ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Hain Portrait Lord Hain (Lab)
- Hansard - - - Excerpts

My Lords, I tabled Amendment 7T and took the liberty of giving the Minister a copy of my draft speech in advance, in the hope of his co-operation and acceptance of the amendment. The Bill as it stands puts at risk a multimillion pound investment in Wales in and around my home area of Neath Port Talbot, which is already facing massive economic haemorrhage resulting from the threat to Tata Steel. The issue at stake relates to an already consented project, Gamesa’s Llynfi Afan renewable energy project, which has had its planning condition varied through a Section 73 consent to allow for a different road access route. The project is ready to start construction, and some of the major work is going to local businesses, with obvious positive implications for jobs, which in that area is welcome.

On 27 August 2013, the Llynfi Afan renewable energy project was granted consent by Neath Port Talbot County Borough Council. Previous consent had already been granted by two other local authorities, Bridgend County Borough Council on 18 July 2013 and Rhondda Cynon Taff on 13 October 2011. However, due to a change in the proposed site access route, the developer, Gamesa, successfully applied for variation of two conditions of the Neath Port Talbot permission by way of Section 73 consent. I stress that the variations dealt solely with the access route for turbine component deliveries to the site of the consented generating station itself, and its capacity will remain unaltered. As such, the impact on the DECC budget is neutral.

The variations were approved on 24 February 2016 by Neath Port Talbot County Borough Council. As I understand it, where an application under Section 73 is granted, the effect of the Planning Act 1990 is the issue of a new planning permission, with a new decision date, sitting alongside the original permission, which remains intact and unamended. The consent and conditions of the original consent are preserved, as is the implementation date by which the construction of the generating station should have been started. On Report in the House of Lords, the noble Lord, Lord Bourne, said:

“Where consent is granted for development on or before 18 June and is subsequently varied”,—[Official Report, 21/10/15; col. 668.]

in this way, it will continue to fall within the approved development condition.

While that is very welcome and positive for this project, regrettably, his statement by itself has proved insufficient to achieve adequate investor confidence. That is because the renewable obligation certificate is awarded after the wind farm has been built and has proven to be exporting electricity to the grid. Investors therefore need certainty before construction, otherwise there is a risk that the project could be built but not receive the required support. As a result, investors wish for certainty reflected in the legislation, and without the amendment the project will be put at risk. The amendment therefore aims to resolve the issue and ensure that the project can go ahead, matching government intent and delivering investment in the local community. My understanding is that without the amendment, such variation permissions as Section 73 would not qualify under the Government’s grace period condition.

The investors’ legal advisers have said that, as the Energy Bill currently stands, it fails to reflect the position that variation consents are fresh planning permissions as a matter of law, as used to be the case. They assert that without an amendment, such variation permissions would not qualify under the Government’s grace period condition. Amending the Bill would make it absolutely clear and avoid any additional funding being added other than what the Government have already allowed for.

In the particular case of Llynfi Afan Renewable Energy Park, tens of millions of pounds will be invested in the construction and operational phases. The communities have widely supported Gamesa’s Section 73 application, as they support the project and wish to see it happen. The local community stands to gain substantially in community benefits, and in terms of business rates and direct and indirect local employment opportunities. Gamesa is in the final stages of appointing a contractor who will be responsible for building the wind farm and, as such, will require employment and services from the locality. It has been Gamesa’s aim to work wherever possible with local companies, involving local jobs, and will continue to do so during the construction and operational phases.

I appeal to the Minister to agree to the amendment. If he finds some technical fault with it—although it is not obvious to me what that might be—will he agree to write a letter to the developers explaining why the Bill as it stands, without the amendment, meets their objectives and that they will be able to proceed, notwithstanding the fact that this amendment may not be accepted by the House?

Lord Wallace of Tankerness Portrait Lord Wallace of Tankerness (LD)
- Hansard - -

My Lords, the Minister has moved Amendment 6 and spoken to Amendment 7, and I want to speak principally to my amendments to Amendment 7. My noble friend Lady Featherstone may say something about the wider issue of the early closure of the renewables obligation in respect of onshore wind generating stations. The Minister has repeated the Conservative Party manifesto commitment that there will be no new subsidies for onshore wind, but I well recall the comment from the noble Baroness, Lady Worthington, that it is difficult to think that a new subsidy is actually the early closure of a long-existing subsidy. The Minister repeats that again and again, but no one is seeking to overturn the early closure. However, the grounds he has stated— that it is a manifesto commitment—are somewhat doubtful.

I have yet to find many people in the industry who think this is a very wise move at all. It is not simply about what is being done with onshore wind; as we have already heard in this debate, a large amount of the investment made in developments over a long period will be cut off at a fairly arbitrary date. The Government’s capriciously cutting off developments in the way proposed affects the confidence of those who want to invest not only in onshore wind renewables but in the entire renewables industry and, indeed, in other infrastructure developments.

Turning to the amendments, I begin by thanking the Minister for his willingness to engage through exchanges of letters and in meetings. One reason why we on these Benches were very happy to support the move to take out the principal clause in the original Bill was not that we did not expect the Government to try to bring back the clause, but that we felt that it would give them an opportunity to reflect on and try to improve the grace periods. Although they were welcome as far as they went, they certainly fell far short of what many people in the industry—I would say almost universally—thought was required.

What has been disappointing, and perhaps not in keeping with the way this House operates when we ask the Government to think again, is that we have absolutely no sense that they are willing to compromise in any way whatever. They have said that there is no compromise, and that is why the amendments that I have tabled—particularly Amendment 7X—embody quite a number of the changes which the industry wants to see and on which we have had representations. I invite your Lordships to support that amendment. I hope that if that measure is brought back in—after all, the Bill has to go back to the Commons because the Government have brought forward amendments to their own amendments—there will be a further opportunity for the kind of engagement that is part and parcel of the way this House operates. Certainly, when I had the privilege of sitting on the Front Bench and dealing with amendments, I tried to find some means of compromise when there were Lords defeats.

--- Later in debate ---
Lord Bourne of Aberystwyth Portrait Lord Bourne of Aberystwyth
- Hansard - - - Excerpts

The noble Lord is wrong on the issue because, with the grace period and with the investment-freeze conditions, we have allowed for movement on these issues. I take the point that he is making but I do not agree with it.

I am just double-checking, but I hope that I have now done full justice to the comments that have been made.

Lord Wallace of Tankerness Portrait Lord Wallace of Tankerness
- Hansard - -

My Lords, I do not think that the Minister has addressed two points, one of which is the investment-freeze conditions and green organisations such as Triodos, which do not appear to qualify. Even at this late stage, would he be prepared to look at this again? I also refer to the points made by the noble Earl, Lord Lindsay, and myself with regard to community investments. I do not think that the Minister has specifically addressed that issue as regards the Dalquhandy and West Douglas development.

Lord Bourne of Aberystwyth Portrait Lord Bourne of Aberystwyth
- Hansard - - - Excerpts

Taking the latter point first, I think that I did so in response to the comments made by the noble Lord, Lord Bruce. We do not see any reason for distinguishing between community projects and others. That would only give rise to difficulties.

On the investment-freeze conditions, I think that the noble and learned Lord is pursuing the lenders point. There is no intention to alter the list. It is something that I think could be done in the future without primary legislation, but there is no proposal to change that. I apologise for not covering it earlier.

I think that I have covered all the main points, and with that, I ask noble Lords to withdraw their amendments.

Amendments 6A and 6B (as amendments to Commons Amendment 6)

--- Later in debate ---
Moved by
7X: Leave out lines 176 to 185 and insert—
“(d) evidence that—
(i) an application for 1990 Act permission or 1997 Act permission was made before 18 June 2015 for the station or for additional capacity,
(ii) the relevant planning authority resolved to grant 1990 Act permission or 1997 Act permission on or before 18 June 2015, and
(iii) planning permission was granted after 18 June 2015, and
(iv) any conditions as to the time period within which the development to which the permission relates must be begun have not been breached, or
(e) evidence that—
(i) an application for 1990 Act permission or 1997 Act permission was made on or before 18 June 2015 for the station or additional capacity,
(ii) the period allowed under section 78(2) of the 1990 Act (or as the case may be) section 47(2) of the 1997 Act ended on or before 18 June 2015 without any of the things mentioned in section 78(2)(a) to (b) of the 1990 Act or section 47(2)(a) to (c) of the 1997 Act being done in respect of the application, except than an extended period has been agreed in writing between the applicant and planning authority for the purposes of section 78(2) of the 1990 Act or section 47(2) of the 1997 Act,
(iii) the application was not referred to the Secretary of State, Welsh Ministers or Scottish Ministers in accordance with directions given under section 77 of the 1990 Act or section 46 of the 1997 Act,
(iv) planning permission was granted after 18 June 2015, and
(v) any conditions as to the time period within which the development to which the permission relates must be begun have not been breached, or
(f) evidence that—
(i) an application for consent for the station or additional capacity was made under section 36 and the consultation period prescribed by regulations made under paragraph 2(3) of Schedule 8 had expired prior to 18 June 2015,
(ii) during the consultation period, the relevant planning authority had notified the Secretary of State that they had objected to the application and their objection had not been withdrawn,
(iii) the Secretary of State caused a public inquiry to be held,
(iv) following consideration of the objection and the report of the person who held the inquiry, the Secretary of State granted consent and deemed planning permission after 18 June 2015, and
(v) any conditions as to the time period within which the development relates must be begun have not been breached, or
(g) evidence that—
(i) an application for 1990 Act permission or 1997 Act permission was made on or before 18 June 2014 for the station or additional capacity,
(ii) planning permission was granted after 18 June 2015, and
(iii) any conditions as to the time period within which the development to which the permission relates must be begun have not been breached, or
(h) evidence that on or before 18 June 2015 the relevant planning authority made a decision to grant planning permission for the station or additional capacity, or made a decision to grant or to intend to grant planning permission for the station or additional capacity, subject to an agreement under section 106 of the 1990 Act (planning obligations) or section 75 of the 1997 Act (agreements regulating development or use of land); and such an agreement is concluded before the onshore wind closure date, or
(i) a declaration by the operator of the station that, to the best of the operator’s knowledge and belief, planning permission is not required for the station or additional capacity.
(5) The documents specified in this subsection are—
(a) a copy of an offer from a licensed network operator made on or before 18 June 2015 to carry out grid works in relation to the station or additional capacity, and evidence that the offer was accepted on or before that date (whether or not the acceptance was subject to any conditions or other terms);
(b) a copy of—
(i) an application for an offer to carry out grid works in relation to the station or additional capacity submitted to a licensed network operator on or before 18 June 2015; and
(ii) an offer from a licenced network operator made after 18 June 2015 to carry out grid works in relation to the station or additional capacity and evidence that the offer was accepted after 18 June 2015 (whether or not the acceptance was subject to any conditions or other terms); or
(c) evidence that planning permission for the station or additional capacity was refused on or before 18 June 2015 and an appeal was determined as at 18 June 2015;
(d) a copy of an application for an offer to carry out grid works in relation to the station or additional capacity submitted to a licensed network operator on or after 18 June 2015; and
(e) an offer from a licensed network operator made after 18 June 2015 to carry out grid works in relation to the station or additional capacity and evidence that the offer was accepted before 31 December 2015 (whether or not the acceptance was subject to any conditions or other terms),”
Lord Wallace of Tankerness Portrait Lord Wallace of Tankerness
- Hansard - -

My Lords, in view of the fact that the Minister has given no concession whatever, I beg to move and then test the opinion of the House.

Lord Faulkner of Worcester Portrait The Deputy Speaker
- Hansard - - - Excerpts

I should inform the House that if Amendment 7X is agreed to, I will be unable to call Amendments 7Y, 7AA and 7AB by reason of pre-emption.

--- Later in debate ---
Moved by
7AA: Line 179, at end insert “, or
“(e) evidence that—
(i) the requirements of section 61W of the 1990 Act or section 35B(2) to (6) of the 1997 Act were met on or before 18 June 2015 for the station or the additional capacity and planning permission for the station or the additional capacity was subsequently granted before this section came into force,
(ii) any conditions as to the time period within which the development to which the permission relates must be begun have not been breached, and
(iii) the station or additional capacity was being developed by a community organisation or an equity shareholding in the station or the additional capacity had been committed to a community organisation(s) on or before 18 June 2015.”