South West Rail Resilience Programme Debate
Full Debate: Read Full DebateLord Tunnicliffe
Main Page: Lord Tunnicliffe (Labour - Life peer)Department Debates - View all Lord Tunnicliffe's debates with the Department for Transport
(1 year, 8 months ago)
Lords ChamberI say, absolutely, that one should not believe everything one reads in the newspaper. It is the case that Network Rail has to work within its funding envelope for CP7, which goes from 2024 to 2029. We are investing a record £44.1 billion in our rail infrastructure—a 4% increase on CP6—so the Government are providing significant funding. As with many elements of the railways, it is important that Network Rail and others look at what funding they have and obtain efficiencies to ensure that the reliability of the railway is maintained.
My Lords, I looked at a recent exchange between my noble friend Lord Berkeley and the Minister on this subject. Essentially, he asked whether funding for phase 5 will be withheld and she gave the heroic non-answer that she has just repeated. Can we be absolutely clear where we are on funding? Will funding be available for phase 5? If not, does the Minister accept that building phases 1 and 4 and not phase 5 is a complete waste of money?