Lord Tunnicliffe
Main Page: Lord Tunnicliffe (Labour - Life peer)Department Debates - View all Lord Tunnicliffe's debates with the Department for Transport
(2 years, 6 months ago)
Lords ChamberI thank my noble friend for that contribution and I have nothing further to add.
My Lords, can we go into this Avanti contract a little more? Modern Railways magazine, which tends to be an authoritative magazine in the industry, says that Avanti will be taking over the service on a national rail contract on 16 October. Can the Minister confirm that that is true? When does she expect to actually conclude the contract with Avanti? Can she explain what revenue risk, if any, Avanti will be taking? Will she perhaps illustrate what other risk Avanti will be responsible for? The key question, I think, given that there is not going to be a competitive process, is: how do we know we are getting value for money?
Avanti already has an emergency recovery measures agreement, which was awarded to First Trenitalia, which is Avanti, in August 2019. That was initially for seven years, so the national rail contract we are currently negotiating with Avanti will replace that. It will start on 16 October if negotiations reach an appropriate point. We will not award the contract if it is not right to award the contract, because, of course, there are alternatives. As for the revenue risks, obviously these contracts operate as all rail contracts do, whereby the Government take on the revenue and the costs; however, the train operating companies do annual business planning every year, which has to be agreed with the department. On that basis, within that, there are various performance measures that have to be met, and that is how we are able to control the railway and ensure companies are delivering value for money.