Baroness Sugg Portrait Baroness Sugg
- Hansard - - - Excerpts

My Lords, this train line has been a long-standing problem ever since it was opened in 1846—that year trains failed to run along it. We are working closely on that and although I am not able to give the noble Lord a date, we are making significant progress. Network Rail has submitted a plan that we are looking at carefully and we hope to make an announcement on it very shortly.

Lord Rosser Portrait Lord Rosser (Lab)
- Hansard - -

First, in very bad weather, as has been said, the Voyager trains used by the CrossCountry franchise are often unable to operate west of Exeter, as electrics on the roofs of the trains are adversely affected by salt water coming over the sea wall in the Dawlish area. Will the new Hitachi trains being introduced on the line also be adversely affected by salt water coming over the sea wall? Secondly, Network Rail’s plan for preventing sea damage is, as has been said, to build a new, higher sea wall, in respect of which it has made a planning submission to the relevant local authority, with the knowledge of the Secretary of State. We know the problem is only going to get worse as sea levels rise, so what happens if that planning application is declined? What is plan B? Or is there no plan B?

Baroness Sugg Portrait Baroness Sugg
- Hansard - - - Excerpts

The noble Lord is right to point to the issues we have with CrossCountry trains. The new intercity express trains on GWR were also affected by weather along the Devon coast last week, so we are working very closely with Hitachi to find a solution. As the noble Lord pointed out, there is a planning submission in play and, as I said, we are absolutely determined to come up with a long-term solution to this problem.