Lord Razzall
Main Page: Lord Razzall (Liberal Democrat - Life peer)Department Debates - View all Lord Razzall's debates with the Department for Transport
(4 years, 3 months ago)
Lords ChamberI reassure the noble Lord that this issue is now in the closely cropped grass so that we can see what is going on, as well as who is doing what and when. At the moment, I am confronted with a library full of engineering reports, at least eight of them, all written by a clutch of probably fairly expensive consultants and commissioned by a plethora of bureaucrats. Somehow we have to bring all this together. I intend to hold an engineer think-in where the engineers will decide on the best solutions for both the short term and the long term. This is not about pushing the issue into the long grass; it is about bringing it into the open and getting the decision-makers to come to a decision.
My Lords, I obviously welcome the commitment of the Minister to treat this as a matter of urgency. I will follow on from the questions put by my noble friend Lady Kramer. Does the Minister not accept that, irrespective of the cost, the only organisation that is going to pay for either the temporary or the permanent solution is central government? Hammersmith, Richmond and Transport for London are clearly not in a position to do so. Does she also accept the enormous urgency of the point made by my noble friend, which is that we must have a temporary solution in the form of either a road bridge or a pedestrian and cycle bridge, as well as a temporary solution for river traffic?
The noble Lord has outlined the challenge that I face with great detail and correctness. In the short term, we need to look at ferries and whether in due course the bridge might be opened to pedestrians and cyclists after remedial works. It is a complex task but not one that is beyond the wit of man, and I think that we can crack on and do it. He also mentioned funding. Over the past 16 months while the bridge has been closed, Hammersmith and Fulham Council and TfL have both been able to find various sums of money. I accept that they have not said that they can bear the full cost of the restoration at £141 million, but in March this year the Mayor of London said that he had committed £25 million. I am not sure where that money went.