Levelling Up: Project Delivery

Lord Kennedy of Southwark Excerpts
Thursday 23rd November 2023

(1 year ago)

Lords Chamber
Read Full debate Read Hansard Text Watch Debate Read Debate Ministerial Extracts
Asked by
Lord Kennedy of Southwark Portrait Lord Kennedy of Southwark
- View Speech - Hansard - -

To ask His Majesty’s Government, following the publication of the National Audit Office report Levelling up funding to local government on 17 November, what action they are planning to take to improve the delivery of projects approved under their levelling-up agenda.

Lord Kennedy of Southwark Portrait Lord Kennedy of Southwark (Lab Co-op)
- Hansard - -

My Lords, I beg leave to ask the Question standing in my name on the Order Paper and refer the House to my relevant interest as a vice-president of the Local Government Association.

Baroness Penn Portrait The Parliamentary Under-Secretary of State, Department for Levelling Up, Housing & Communities (Baroness Penn) (Con)
- View Speech - Hansard - - - Excerpts

My Lords, the department has implemented several measures to support local authorities in their delivery of levelling-up projects. These include committing over £65 million for capacity support to unblock delivery issues and giving authorities greater flexibility over spending decisions. The National Audit Office report covers the progress of projects up to March 2023, and in the eight months since then the department has paid out over £1.5 billion of further funding to local authorities.

Lord Kennedy of Southwark Portrait Lord Kennedy of Southwark (Lab Co-op)
- View Speech - Hansard - -

I thank the noble Baroness for her comments. The report from the National Audit Office makes shocking reading: it tells of money allocated but not spent, contracts not signed and projects not delivered. Can the Minister explain to the House how a flagship programme of the Government is in such a mess?

Baroness Penn Portrait Baroness Penn (Con)
- Hansard - - - Excerpts

My Lords, the report itself highlights a number of issues that have delayed some of the delivery, including rising costs and inflation and other outside factors. That is why we are working with local authorities to address those issues. As I say, in the eight months since the report, the department has paid over £1.5 billion of further funding out to local places. We have already seen several projects completed or near completion, which are making a difference to the lives of people in those communities.