Electricity Network Connection Action Plan Debate
Full Debate: Read Full DebateLord Grantchester
Main Page: Lord Grantchester (Labour - Excepted Hereditary)Department Debates - View all Lord Grantchester's debates with the Department for Energy Security & Net Zero
(1 year, 1 month ago)
Lords ChamberMy noble friend asks good questions. The figures are that peak demand for electricity is expected to increase from 47 gigawatts in 2022 to between 90 and 120 gigawatts in 2035, as transport, heating and industry electrify. We think that this will require between 260 and 310 gigawatts of generation capacity connected to the network by 2035. To do all these things, we of course need to reform the planning system, which we are doing through national policy statements and through the action plan announced today.
My Lords, there are considerable problems with capacity issues within local circuits in the distribution network from the transmission lines, especially in rural areas. There are reported delays even to the 132-kilovolt networks, as renewable schemes are being held in the queue to be connected until 2037. How can that help to decarbonise the power sector by 2035? I declare an interest as being involved in such a scheme. Will the plan published today help to resolve this queue and reappraise the first-come-first-served basis for supply connections?
The noble Lord points to the main problem that we have, which is that there is a large queue of projects running into many hundreds of gigawatts. The whole purpose of the action plan is to look at which of those projects are likely to go ahead and to prioritise those that are likely to proceed—a lot are in the queue and probably not likely to proceed—and have the investment and backing, and will decarbonise and deliver the upgrades as quickly as possible. I am not familiar with the particular project that the noble Lord referred to, but if he wants to send me the details, I will certainly look at it for him.