Infrastructure Planning (Water Resources) (England) Order 2018 Debate

Full Debate: Read Full Debate
Department: Department for Environment, Food and Rural Affairs
Wednesday 21st November 2018

(6 years, 1 month ago)

Grand Committee
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Gardiner of Kimble Portrait Lord Gardiner of Kimble
- Hansard - - - Excerpts

My Lords, the Government are pushing for it on behalf of the nation in so far as we undertook consultation. With climate change and population growth, we need to prepare. We wish to place a greater emphasis on the environment and therefore to deal with overabstractions. We need to find ways of having sufficient water, given the projections of an increase in population. This is about planning. We do not expect the projects to which this measure will apply to take place in the next five years; this is about forward planning. We think that these changes will probably embrace about six projects in England. The noble Lord asked who is driving this. We need to take a public responsibility to ensure that there is sufficient water for the nation. Yes, we should cut consumption where we can, but, because of population growth and climate change, we are bringing forward this measure now as part of our forward planning. It will involve public engagement, but that is the background to it.

On conclusions and criteria, we needed to make sure that we consulted, so we consulted on our initial proposals last November and then held a more detailed consultation in April. There was broad support for our approach from a range of stakeholders who responded, including water companies, environmental groups and other interested groups.

In reaching a conclusion on the new thresholds, we considered a number of factors, including the physical size of the infrastructure in question, the size of population that could be served by its output and the major infrastructure the Government anticipate will be needed in future. This is likely to require developers to engage with a number of planning authorities and other regulatory regimes. We also wished to move to a level playing field so that different water resource schemes are all required to meet thresholds that are as consistent as possible to qualify for consideration under the Act. This should help avoid developers favouring one scheme over another just because they prefer one planning route over another.

In making these amendments, we are introducing a consistent metric to measure the output of each infrastructure type. This metric is known as deployable output and is commonly used by the water industry for water resource planning. Deployable output is an annual average measure of the number of litres of water a particular piece of infrastructure can be expected to produce in a day under drought conditions. We concluded that a project expected to have a deployable output of 80 million litres per day—a level that could serve a population of around half a million people—is a nationally significant infrastructure project.

As explained, the order will amend qualifying thresholds for two existing infrastructure types mentioned in the Act and introduce a third—desalination plants. In the case of water transfers, this order would reduce the size of the threshold that projects would need to meet to qualify as nationally significant in line with the number of people served—that is, 80 million litres per day.

There will now be two ways for reservoirs to qualify for the streamlined planning process under the Act. The order would introduce a deployable output measure, consistent with transfers. However, we have chosen to retain a measure based on physical volume, recognising that the size of reservoirs matters. This is not just because of the impact they can have on neighbouring communities, but because a large reservoir takes a long time to drain down. Thus, with a relatively low deployable output, it can be an important part of overall water resource resilience. We have increased the volume for reservoirs to qualify under the Act from 10 million cubic metres to 30 million cubic metres.

We have also introduced desalination plants as a new infrastructure type. Consistent with the other infrastructure types, if the deployable output of a given desalination plant is expected to exceed 80 million litres per day, the project can be considered under the Act.

While the national level is the right one for decisions on nationally significant infrastructure, it is vital that those communities directly affected have their say and are heard in the decision-making process. The Act and regulations made under it set out the consultation requirements for development consent order applications. I can assure your Lordships that extensive pre-application consultation and engagement with those affected by the proposals will need to be undertaken by applicants. Furthermore, members of the public can participate in the examination process by registering their interest, thus ensuring that local views can be heard.

The main benefit to the developer of projects meeting the criteria in the Act is that they will face a less complex, consenting process with quicker decision-making. A number of consent requirements, such as planning permission, listed buildings consent and scheduled ancient monument consent, are replaced by a single consent, issued by the Secretary of State, following advice provided by the Planning Inspectorate.

It is the Government’s intention to designate a national policy statement for water resources infrastructure under the Planning Act. This policy statement will summarise government policy—

Lord Geddes Portrait The Deputy Chairman of Committees (Lord Geddes) (Con)
- Hansard - -

My Lords, it has just been drawn to my attention that a Division has been called in the Chamber. Since we have a few seconds to go until 6.25 pm, the Grand Committee therefore stands adjourned until 6.35 pm.