Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

The noble Lord is right to raise the increasing costs of transport infrastructure projects. Noble Lords may know that I have a particular interest in Hammersmith Bridge at the moment. It was built for £10 million in today’s money many, many years ago; you could not get it for that now. I take the noble Lord’s point that we absolutely have to drive down costs. That is part of what we are doing with Network Rail. It is really important that we challenge the costs and make sure that they are as low as possible. If the noble Lord has any evidence that he wants to share with my department and the rail Minister, I would be happy to pass it on.

Lord Bradshaw Portrait Lord Bradshaw (LD) [V]
- Hansard - -

My Lords, the industry and its suppliers want, most of all, a steady and consistent workload. Will the Minister stress to her department, and the Treasury, the need to plan ahead so that this might happen?

Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

The noble Lord is quite right, and that is one of the reasons why we have investment periods for both rail and roads. This makes sure that the supply chain knows what is coming down the track, so to speak, and is able to respond accordingly. It also gives it certainty that if a project goes through its stages then it will actually happen. One of the biggest challenges we have had previously has been a lack of certainty that projects will happen. The noble Lord will also know that the spending review has been reduced to one year. However, for some of the long-term plans—for example, CP6 for rail—it will be a multi-year settlement.