Great Western Main Line: Electrification Debate

Full Debate: Read Full Debate
Department: Department for Transport

Great Western Main Line: Electrification

Lord Bradshaw Excerpts
Tuesday 14th March 2017

(7 years, 1 month ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Ahmad of Wimbledon Portrait Lord Ahmad of Wimbledon
- Hansard - - - Excerpts

The noble Lord is right to raise the issue of Swansea but I believe I have already addressed that. It will be considered as part of the CP6 expenditure. However, to put this into context, £2.8 billion is specifically allocated to the electrification of the Great Western line. We are talking about 170 bridges, 1,500 sets of foundations, 14,000 overhead lines, 1,500 pieces of signalling equipment and 17 tunnels. Notwithstanding that, the Government are making investments, as I am sure the noble Lord acknowledges. The rollout of new rolling stock, which will start to be applied to the line from the end of this year, will ensure better and more efficient customer service across the whole network.

Lord Bradshaw Portrait Lord Bradshaw (LD)
- Hansard - -

My Lords, the Great Western railway electrification scheme was designed in the Department for Transport; it was specified there and the trains were ordered there. However, the new trains and the new system will not provide a faster or better service than was the case 40 years ago, when I was general manager at Paddington. In future, will the Government look very carefully at whether there are better design and procurement methods to ensure that we get a scheme that delivers benefits to passengers and saves the taxpayer money?

Lord Ahmad of Wimbledon Portrait Lord Ahmad of Wimbledon
- Hansard - - - Excerpts

I do not agree with the noble Lord’s premise. I believe that the new rolling stock that I referred to will bring passenger benefits. As I am sure he knows from his experience in and vast knowledge of the area, the IEP fleet, which is coming into service on the whole route, will run in both diesel and electric modes. That will provide flexibility in the delivery and appropriate scheduling of the electrification programme, which I accept is challenging.